GAZİPAŞA II.STAGE PROJECT – GÖKÇELER DAM SUPPLY CONSTRUCTION

Administration: DSİ 13th Regional Directorate
Location:  13 Km Northeast of Gazipaşa County Centrum
Purpose: Potable Water + Energy+ Irrigation
Body Type:  Concrete Covered Rock Fill Dam
Height of Thalvegden: 98 m
Thalweg level: 102.00 m
Elevation from Base: 103 m
Base Elevation: 97.00 m
Crest Elevation: 896 m
Crest Length: 362.73 m
Total Body Volume: 1.819.152,53 m³
Reservoir Volume: 56.830,000 m³
Diversion Tunnel Number: 1 piece
Diversion Tunnel Length: 384.98 m
Diversion Tunnel Inner Diameter: 4.00 m
Spillway Type: Thick Edged, Input from Front, Uncontrolled Gradual
Spillway Project Flow Rate: 592.85 m³/sn
Duration of Work:  2015-2017