KARACABEY – YEŞİLDERE DAM
Administration: DSI 1st Regional Directorate
Place:Located in the West of Karacabey District of Bursa Province, 1 Km from Yeşildere Village
Purpose:Irrigation
Body Type:Concrete-Fronted Rock Fill Dam
Height from thalweg:57.50m
Talweg Jean:79,50 m
Height from foundation:67.00 m
Foundation Level:70.00 m
Crest Jeans:137 m
Crest Length:318,95 m
Total Body Volume:786 668 m³
Reservoir Volume:16.000.000 m³
Number of Diversion Tunnels1 piece
Diversion Tunnel Length:407,04 m
Diversion Tunnel Inner Diameter:3.00 m
Spillway Type:Purchase Uncontrolled
Spillway Project Flow:122,85 m³/s
Time of work:2014-2018